teapawt
$
151FrontStW
@151FrontStW
151 Front St. W., Toronto, ON
Joined June 2010
Tweets
27
Following
28
Followers
88
Likes
0
Tweets
All
Posts
Sort by
Most recent
Popular
Tweets & Replies
Reposts
Media
Search
151FrontStW
@151FrontStW
14 Aug 2017
Diesel Day is now set for Oct 28th, 6AM to 6PM
#DieselDay
#151Front
1
151FrontStW
@151FrontStW
15 Feb 2017
Diesel day in April has now been postponed - likely to be rescheduled for September
151FrontStW
@151FrontStW
13 Feb 2017
Diesel Day is April 8th
151FrontStW
@151FrontStW
14 Apr 2012
Annual power maint completed. Back on commercial power.
1
1
151FrontStW
@151FrontStW
14 Apr 2012
Annual power maintenance begins at 7am
1
2
151FrontStW
@151FrontStW
29 Jun 2011
There is a guy giving away free bottles of Stella across the street from 151
151FrontStW
@151FrontStW
9 Apr 2011
Most tenants back on commercial power
151FrontStW
@151FrontStW
9 Apr 2011
Beginning to restore commercial power
151FrontStW
@151FrontStW
9 Apr 2011
Lunch is ready
151FrontStW
@151FrontStW
9 Apr 2011
Schedule resumed after issues to 3rd floor rectified.
1
151FrontStW
@151FrontStW
9 Apr 2011
Running 1 hour behind schedule
151FrontStW
@151FrontStW
9 Apr 2011
Reports of power issues on the 3rd floor
151FrontStW
@151FrontStW
9 Apr 2011
Officially running 20 minutes behind schedule
151FrontStW
@151FrontStW
9 Apr 2011
Beginning high voltage isolation
151FrontStW
@151FrontStW
9 Apr 2011
Generators starting,
#dieselday
at
#151front
begins
151FrontStW
@151FrontStW
9 Apr 2011
A little more than 1 hour before we start the generators at
#151front
for
#dieselday
151FrontStW
@151FrontStW
8 Apr 2011
Generators have begun to arrive to prepare for diesel day tomorrow.
1
151FrontStW
@151FrontStW
30 Mar 2011
Annual power shutdown "diesel day" is April 9th
151FrontStW
@151FrontStW
5 Jul 2010
Power in the lobby and some hallways is still out. Chilled water is also affected
1
151FrontStW
@151FrontStW
5 Jul 2010
Power has been restored
1