Transwestern Pipeline declared force majeure effective November 19, 2026 due to a compressor station mechanical failure on the West Texas Lateral.
#natgas
10
693
U.S. gas supply bounced back.
Pipeline receipts: 69.14 Bcf/d Nov 14–17, up 2.4 Bcf/d from the early-November dip. 69.64 on Nov 15 was the highest November day in our data.
Appalachia +1.2, Haynesville +0.8. Pipeline maintenance is nearly done.
enercast.com/news/us-gas-sup…
NGPL has declared force majeure at Compressor Station 168 in Bailey County, Texas (Segment 8, Permian Zone) due to a unit outage, effective gas day November 19, 2026, continuing until further notice.
#natgas
9
823
Unplanned TGP force majeure at Sta 542 threatens up to 0.25 Bcf/d of firm capacity with no restoration timeline. #natgas
4
781
Which U.S. gas pipelines are actually getting built?
New: Enercast tracks 99 pipeline projects of 0.2 Bcf/d+, from announcement to in service. 40.1 Bcf/d of stated capacity is under construction.
Each status and date sourced to FERC, EIA or the sponsor.
enercast.com/news/new-pipeli…
Getting some inquiries on this one so wanted to clarify:
There are 4 lines feeding Sabine Pass (Creole Trail being one of them). This work only caps the Creole Trail leg at 1.13bcf. So it would be a 0.4bcf reduction from their current (today's) 1.51 levels
1
207
Sabine Pass #LNG can be tracked here: enercast.com/daily-summary/c…
117
Some bigger moves in today's early cycle pipe flow data #natgas
Canada is sending less gas south.
Net U.S. pipeline imports from Canada: 5.66 Bcf/d Jan–Oct, down 13% on the year. Every month of 2026 is below 2025.
Same period: LNG Canada took an estimated ~1.4 Bcf/d more gas at Kitimat.👇
enercast.com/news/canada-gas…
Cove Point LNG critical operational alert with no stated cap or curtailment volume; pre-event feedgas delivery was running ~0.86 Bcf/d (loc 10001 D:DPQ, 93.3% utilized, only 0.061 Bcf/d headroom), so any reduction is bearish for Appalachian supply demand and bearish for the LNG export arb #natgas
8
633
Pipeline maintenance season is over. Unplanned outages aren’t.
Planned outages on U.S. interstate gas pipelines: 18 in August → 5 in October.
Unplanned: 23–28 every month since June, with no seasonal letup.
Capacity offline peaked at 4.18 Bcf/d on Oct 28.
Charts + what’s still scheduled into December 👇
enercast.com/news/pipeline-m…
U.S. gas supply, now by basin. Daily.
Appalachia, Haynesville, Permian and 8 more, from actual pipeline nominations. Rows add up to the national total, so you can see where a move came from.
Free on #enercast 👇
enercast.com/news/supply-by-…
Record October for U.S. #natgas supply. Then Nov 1 happened: −3.26 Bcf/d in one day.
Nearly all of it in two basins: Appalachia and Haynesville.
Our pipeline data, by basin, and what $EQT told investors 👇
enercast.com/news/supply-dro…
Existing EPNG FM increased capacity reduction and extended another day through Nov 4
#natgas
4
656
Transwestern update on existing notice extends force majeure another day through Nov 4
#natgas
419