M28 Cork to Ringaskiddy Project retweeted
M28 update The existing Maryborough Hill Bridge was successfully demolished by Cork County Council over the October Bank Holiday weekend as part of the €456 million N28 Cork to Ringaskiddy Motorway Scheme. This milestone marks another significant step forward in the delivery of this important infrastructure project. For more information on the M28 project, visit: bit.ly/4zhf5B7
2
2
5
2,224
More footage from the successful bridge demolition last weekend. This key milestone paves the way for the next phase of works and the new permanent bridge to be built. 👏🌉
4
7
1,829
A significant milestone reached this weekend with the demolition of the Maryborough Bridge. Thank you to residents and motorists for your patience and co-operation throughout the works. BAM engaged specialist demolition contractor O’Kellys to safely undertake the demolition. 🌉👏
5
29
13,448
The N28 has now fully reopened following the bridge demolition works over the weekend.
1
2
2,311
Replying to @NiallOShea
Niall, Maryborough Hill Road is now open to traffic.
63
Maryborough Hill Road is now open to traffic following demolition works. The N28 remains closed as crews continue works and will reopen as planned.
3
2,067
Due to adverse weather conditions and the bridge demolition works taking longer than anticipated, Maryborough Hill Road will remain closed and will reopen tomorrow, Sunday 25 October.
2
1
4
3,592
Temporary Bridge on Maryborough Hill open today, 21st of October 🌉👏 Please drive with reduced speed and proceed with care as motorists get familiar with the new temporary layout. #M28
2
751
N28 Maryborough Hill Bridge Demolition October Bank Holiday Weekend 🏗️🛣️ Head over to the our website via the link to see more information on the upcoming closure. m28.ie/n28-maryborough-hill-…
976
Timeline and 4D Visualisation of the New Maryborough Hill Bridge 🏗️🛣️ A 4D visualisation of the Maryborough Hill Bridge works is now available to view. The model provides an overview of the key construction stages associated with the project.
1
2
1,160
Check out our latest newsletter! If you haven't subscribed, use the link at the end of the page to sign up. 📬 mailchi.mp/corkrdo/m28-progr…
568
Collision Northbound on N28 Carrs Hill at end of climbing lane. Take care on approach.
657
A Temporary Road Closure on the R609 Carrs Hill Southbound Onslip onto the N28 for traffic travelling in the direction of Carrigaline/Ringaskiddy will be in place from 8pm Thursday (July 30th) to 6am on Wednesday (August 5th) for works to the Junction. See M28 website for details
1
1
1,063
M28 Cork to Ringaskiddy Project: The temporary bridge at Maryborough Hill was lifted into place on Friday night. Over the weekend, crews completed bridge works and drainage & duct crossings on the N28. Thanks to everyone for your patience and cooperation. 👏 #M28
3
15
1,972
*REMINDER* N28 Carrs Hill Closure 8pm July 24th – 5am July 27th 🛣️🏗️- Carrs Hill will be closed to facilitate installation of a temporary bridge. Click the link below to see diversion routes. m28.ie/n28-carrs-hill-closur…
1
844
M28 Cork to Ringaskiddy Project retweeted
Take a virtual journey along the future M28 motorway! A new interactive 3D Tour is now live, giving you the opportunity to explore key locations along the Cork to Ringaskiddy route from a whole new perspective. - Click on a location such as Carrs Hill, Shannonpark, Maryborough Hill or Shanbally to enter a 3D panorama. - Look around and explore the area from different angles. - Click "Exit Panorama" to return to the map and choose another location. Take the tour: m28.ie/3d-tour/
1
6
1,264
N28 Carrs Hill Closure 8pm July 24th – 5am July 27th 🛣️🏗️- Carss Hill will be closed to facilitate installation of a temporary bridge. Click the link below to see diversion routes. mailchi.mp/corkrdo/m28-progr…
1
1,377
New Temp. Road Layout at Bloomfield Southbound Direction where Traffic Merges from N40 to N28. Drive with Caution.
1
2
3
2,625
Replying to @JaneDel56104188
@JaneDel56104188 Apologies for the delay in reply, we ran into some issues with Google but these have been resolved and the app is back on the store.
1
94