Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)Photo by Midstream_MES (@Midstream_MES)
#Eskom regrets to announce that Stage 1 #load_shedding will be implemented from 06:00 until 22:00 today.
60
120
11
Eskom regrets to announce that: Stage 1 #load_shedding will be implemented from 08:00 until 14:00.
32
64
6
#PowerAlert: Eskom regrets to announce that Stage 1 #load_shedding will be implemented from 17:00 to 22:00 today.
24
86
7
#load_shedding prognosis for today is medium for the morning and very high for the evening & dependent on the performance of the power plant
26
85
9
Any unexpected changes on the vulnerable & constrained system could lead to a change in the stage at short notice. We will keep you updated.
12
19
1
#PowerAlert: Due to the vulnerable system partial Stage 3 #load_shedding will be implemented from 16:00 to 22:00.
52
113
16
RT @Eskom_SA: Please note that stage 2 #load_shedding will resume from 06h00 to 22h00 tomorrow, 15 April.
38
95
7
#PowerAlert: We regret to announce that stage 2 #load_shedding will be implemented from 10:00 to 22:00 today.
52
202
10
Stage 1 #load_shedding will be implemented from 12:00 to 22:00 tonight.
29
49
5
Stage 2 #load_shedding will be implemented on Sunday from 08:00 to 22:00 as the system remains constrained.
55
105
14
Stage 2 #load_shedding will be implemented on Saturday from 08:00 to 22:00 as the system is constrained.
87
190
28
Low to medium probability of #load_shedding today as the system remains constrained. Thank you for using electricity sparingly.
45
77
14
As the system remains constrained, there is a high probability that we may move to stage 2 in the evening. We will inform you accordingly.
36
99
10
Medium to high probability of #load_shedding today. We ask our customers to continue using electricity sparingly to help reduce demand.
13
67
5
Midstream_MES retweeted
There's 50% probability of load shedding today. Any unexpected changes on an already constrained power system could result in load shedding.
38
152
15
Midstream_MES retweeted
#PowerAlert: Stage 2 load shedding will be implemented from 08h00 to 22h00 today as the power system remains constrained.
67
126
20
Midstream_MES retweeted
#PowerAlert: Stage 2 #Load_shedding will be implemented from 08h00 to 22h00 today.
50
155
8
Midstream_MES retweeted
#Eskom: Stage 2 #load_shedding will be implemented from 08:00 to 22:00 today.
44
177
14
Midstream_MES retweeted
The power system remains constrained. Stage 2 #Load_shedding will be implemented from 8:00 to 23:00 today.
27
152
14
Midstream_MES retweeted
#PowerAlert: #Loadshedding will move into stage 2 from 14h00. This is as a result of power station units not returning to service as planned
23
94
6