Today was the day work on the viewing platform started. It's quite big. The view of the building site will be incredible.
Have been into school this week. Viewing platform is finally ready (up in week of 29th Aug). Webcam is installed. Lots to look forward to!
Been on site today. Roof structure is almost in place. Colours for the classrooms / furniture and IT equipment almost ready to be ordered!
Roof is going on now - and quickly! The field is flat - ready for the new football pitch and play areas. Pic attached
Busy week! Pensby Post coming home tomorrow with a page on the new school. Some great pictures - watch out for it!
Sorry not 'tweeted'! Building still on schedule. Choosing colour schemes! ICT being organised - hoping dual touch LCD screens in classrooms!
The concrete floors are in and the building is taking shape. Next week we (the staff) begin to design the detail of the outside spaces - wow
More good news - over the next few days the viewing platform and webcam will be constructed! The concrete floors are almost complete too!
Tomorrow - meeting to start process of ordering all the new furniture.On Friday we looked at interactive plasma screens for the classrooms!
Went into school - steel structure is complete! Over next weeks the roof & walls are being constructed. Meeting on Weds so more news then!
Lots of activity on the site today. I'll be going in to see the progress on Wednesday and Thursday next week. Will update then!
What to do? We need to decide what IT to have in the new school! The chdn use amazing IT gadgets at home - so it has to be the best!
Today was the first meeting on site. The building is on track to be finished as expected! Class visits are now planned for next 1/2 term.
A great day! The School Council visited the new building site office. The building looks HUGE! We enjoyed finding out how the site is run.